Technologies
Title: | Method/Process for Instant Improvement of Foundation Soil during Box Jacking Operation without Affecting the Live Rail/Road Traffic Thereof |
Area: | Agricultural Sciences |
Focus Area: | Improvement of Foundation Soil |
Social Benefits: | No disruption to rail/road traffic during installation of ground improvement measures, Safe, easy and secured technology, Environmental friendly due to less disturbance to the sub soil, No involvement of crane heavy equipment, Less time required to complete the project, Less manpower machinery is required, Reduction in vertical and differential settlements, No chance of tilting of box due to safe and secured alignment, Load bearing capacity of ground is improved at low cost |
Developing Agency: | CSIR-Central Road Research Institute (CRRI), Delhi |
Technology Readiness Index: | Technology Demonstration |
Email: | director.crri@nic.in |
Website Link : | http://www.crridom.gov.in |
Source (more info) : | https://t.ly/l_sb |
Brief Description
Description : | This invention provides the process/method for facilitating the implementation of instant bearing capacity measures during the box jacking operation for construction of underpass below live rail/road traffic. This process will be fruitful where the implementation of ground improvement measure is very difficult due to site constraints from the ground surface. |